1. Purpose of the High-Low Method
Because semi-variable costs contain both fixed and variable elements, managers cannot use them for forecasting without separating the two pieces. The High-Low Method is a straightforward mathematical technique that separates these components by analyzing the costs at the highest and lowest levels of activity.
2. Step-by-Step Calculation Protocol
- Step 1: Identify the periods with the highest and lowest activity levels (volume), and note their matching total costs.
- Step 2: Calculate the variable cost per unit using this formula:
Variable Cost per Unit (b) = (Cost at Highest Activity − Cost at Lowest Activity) ÷ (Highest Activity Level − Lowest Activity Level)
Step 3: Calculate the total fixed cost by substituting the variable cost per unit back into either the highest or lowest activity data point:
Fixed Cost (a) = Total Cost − (Variable Cost per Unit × Activity Level)
3. Mathematical Forecasting Model
Once you calculate these values, you can express the cost structure as a linear equation (Y = a + bX) to forecast total costs (Y) for any future activity level (X).